Substation Scout

Replacing 50 MW of Solar with Nuclear; Duane Arnold

MISO queue ID R5070

Replacing 50 MW of Solar with Nuclear; Duane Arnold (R5070) was listed in the MISO interconnection queue at the end of 2025 as a 64 MW nuclear project in Linn County, IA, according to Berkeley Lab’s queue data file. The filing names Duane Arnold (ARNOLD 5) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2029.

Queue IDR5070
Project nameReplacing 50 MW of Solar with Nuclear; Duane Arnold
Status (as published)Active
SubstationDuane Arnold (ARNOLD 5)
Point of interconnectionDuane Arnold (ARNOLD 5)
CountyLinn
StateIA
VoltageNot reported
Capacity64 MW
Resource (as published)Nuclear
Resource categoryNuclear (normalized for filtering)
Proposed online date2029-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Duane Arnold (ARNOLD 5) substation: 4 requests in the MISO queue, 4 active totaling 615 MW.

Queue IDProjectMWResourceStatus
R5071Replacing 244 MW of Solar with Nuclear; Duane Arnold251NuclearActive
R5069Replacing 200 MW of Solar with Nuclear; J1444200NuclearActive
R5072Replacing 100 MW of Solar with Nuclear; Duane Arnold100NuclearActive

Linn, IA: 26 requests in the MISO queue, 16 active totaling 3,679.9 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC MIDWEST
Project typeGeneration
Queue date2025-08-26

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first