October 27, 2026 · By Phil

Project Kirkland Part 3 — Picking a winner, badly

Three criteria I held back on purpose, a gas screen that knocked out my first winner by a quarter mile, and a moratorium I almost let knock out my second.

Part 3: Picking a winner, badly

Part one narrowed 617 Costco warehouses to 41 on five criteria. Part two cut those to 24 on electricity cost, then tried to check what's queued at their substations and could only answer for eight.

Time to pick one.

This is the part where the data stops helping, and I want to be loud about that before I start, because everything from here on is me making things up.

The three criteria I held back

In part one I declared five screens — load, shell reuse, flood, transmission voltage and gas — and ran them honestly. I also had three more in my pocket that I deliberately didn't publish, because I wanted the funnel to be reproducible before I started editorializing.

Criterion six: queue signal, read both ways. Nearby interconnection activity means either that the path is live and somebody else has proven it works, or that a competitor is already ahead of you in line for the same headroom. The data does not tell you which. That ambiguity is the single most useful thing on this list and no tool will resolve it for you.

Criterion seven: who you negotiate with. Investor-owned utility, municipal, or co-op changes the entire shape of a large-load conversation — the tariff, the security you post, the speed, who has to approve it, and whether there is a commission proceeding in the way.

Criterion eight: the food court stays. Non-negotiable. Site selection is done by humans who eat lunch.

That last one is a joke, but it is doing real work as a joke. It is the criterion that no dataset contains, that I cannot justify, and that would absolutely survive into a real client's requirements under a different name — "amenity retention," "community goodwill," "the mayor likes it." Every site search has two or three of these. Pretending otherwise is how you end up trusting a score.

The winner I lost on the way here

I should tell you that I ran this whole series once before, without the gas screen and with a 345 kV floor. That version had a winner: Covington, Washington, a Costco 0.54 miles from a 500 kV substation, the shortest distance to 500 kV of all 617 Costcos in America, in a state with some of the cheapest industrial power in the country.

Covington's nearest mapped gas pipeline is 1.27 miles away. My gas screen is one mile. So my old winner went out in the first round of the new version, by about a quarter of a mile, on a threshold I picked myself.

I could move the line to keep it. I'm not going to, because I set the one-mile rule before I knew who it would hit, and changing a rule after you see who it hits is exactly how a screening exercise turns into a justification exercise. But I want you to see it happen. A single number I chose decided which state this series ends up in.

Covington is still a site worth looking at twice, so I've posted its Site Scanner report as a bonus sample report (PDF), alongside the 41.

The Pacific Northwest went with it. My first pass spent a lot of time on BPA's queue, which turned out to include 49 gigawatts of requests to consume power — that's now the Large Load Registry, and it's a better story than anything in this post. But with Covington, Wilsonville, Spokane and Tumwater all out on gas, the only Northwest site left on the list is Eugene, and it doesn't make my final two.

The two finalists

Pottstown, Pennsylvania. 1.32 miles from Limerick, which the public record lists as both a 230 kV and a 500 kV substation. Five queue projects across both, one active: C01-1055, 348 MW, nuclear. Four withdrawn, including a 500 MW gas project and a 75 MW one. Columbia Gas Transmission is mapped 0.01 miles away. PECO Energy, investor-owned. Pennsylvania industrial power at 11.04 cents.

Mt. Juliet, Tennessee. 1.61 miles from a 500 kV substation named Wilson. The federal inventory lists ten lines at Wilson and a 161 kV low side, so it steps 500 kV down onto the regional network. Three interstate gas pipelines are mapped within 0.7 miles: Texas Eastern at 0.37, Gulf Xpress at 0.38, Columbia Gulf at 0.67. Middle Tennessee Electric, a member-owned cooperative that buys its power from TVA. Tennessee industrial power at 7.13 cents. And a queue I can't see, because TVA isn't in my data.

This is the twist I didn't see coming in part one. Wilson was my favorite oddity on the first list: a co-op with a 500 kV neighbor, an interesting conversation. Add gas and it isn't an oddity anymore. It's the site that best fits what Project Kirkland asked for.

How they compare

On cost, Mt. Juliet wins by a distance. At a 50 MW round-the-clock load, Tennessee's 7.13 cents versus Pennsylvania's 11.04 is $17.1 million a year. Over a fifteen-year hold that is most of a building.

On gas, both pass easily, but they pass differently. Pottstown has one interstate line right next to it. Mt. Juliet has three different interstate systems within a mile. If the whole point of the gas screen is a plan B, three operators is a better plan B than one: more than one company you can call about a tap. Neither map says any of them would say yes.

On criterion seven they're very different conversations. PECO is an investor-owned utility with a state commission and a lot of large-load experience in the PJM market. In Mt. Juliet you're talking to a cooperative, and behind the cooperative is TVA. That could be faster or slower than PECO. I don't know.

On criterion six they tell opposite stories. Pottstown's substation has a documented history of people trying and failing — 500 MW of gas that didn't finish, two small nuclear entries withdrawn. You can read that as a warning about interconnection difficulty or as just what a busy substation's paper trail looks like. Mt. Juliet has no paper trail at all in my data, and that's not because it's empty. It's because I haven't loaded TVA's queue.

The pick

Mt. Juliet, Tennessee.

Here is my reasoning, and I'd ask you to notice how much of it is not data.

The cost gap is the only part of this I'd defend to a board. $17.1 million a year, every year, is a bigger number than any uncertainty I have about queue position, and energy cost is the one variable in a data center's operating model that never stops compounding. Everything else on my list — voltage, distance, flood zone, gas — is a gate you pass once. Rates are a bill you pay forever.

The gas is the tiebreaker the client asked for. Three interstate pipelines within a mile is the most plan B on the list.

And the blank queue is a bet. In my first pass, I bet that Covington's empty queue meant opportunity. This time I'm betting on a queue I haven't even looked at. That is a guess, and a bigger one. A real site selector would spend the next two weeks on the phone with Middle Tennessee Electric and TVA, and might well come back and tell me Wilson is spoken for.

Pottstown is the better documented site. Its substation has a paper trail and its utility runs a process I can read. If your risk tolerance says "show me evidence somebody else got power here," Pottstown wins and I won't argue.

Also, I checked google maps and the hotdogs are there and they're $1.50. So we're set.

The moratorium in the file

Before anyone books a flight: there's something in Mt. Juliet's report I didn't read until after I'd picked it.

Every Site Scanner report carries an appendix on local moratoria. Mt. Juliet's lists one for a jurisdiction that contains the site: Wilson County. On July 20, 2026 the county commission passed a temporary six-month moratorium on land use, zoning, building, site plan and conditional use permit applications for data centers, and set up a committee to write permanent rules. As of late September the dataset records it as active, with a draft zoning resolution headed to committee in October and an extension possible if the rules aren't done in time.

That was sitting in a PDF I published alongside part one. My first reaction was to throw the site out and hand the win to Pottstown.

Then I checked where the Costco actually is. According to the Census Bureau, the parking lot sits inside Mount Juliet's city limits. In Tennessee, county zoning covers the unincorporated parts of the county; cities zone their own land. So Wilson County's moratorium most likely doesn't reach this site, and I haven't found a Mt. Juliet moratorium of its own. I haven't confirmed any of that with either planning office. That's a phone call, not a dataset.

This is a good example of what a scan can and can't do. The report found the moratorium because Wilson County contains the site, and that's a fact about a map. Whether it applies is a legal question, set by the resolution's own text and by who holds zoning power where, and nothing in my data reads that. The scan put it in front of me; it didn't answer it. It cuts the other way too. A report that shows no moratorium means one third-party dataset hasn't recorded one yet, not that one doesn't exist, and a city council can pass one next month.

So Mt. Juliet stays the pick, and the call list gets one more number: Mt. Juliet's planning department, right after Middle Tennessee Electric and TVA.

What this series was actually about

Every number across these three posts came from public data with a citation: 617 warehouses from OpenStreetMap, substation voltages and distances from HIFLD, flood zones from FEMA, gas pipelines from EIA, queue positions from PJM, ERCOT and BPA, electricity rates from EIA. You can check all of it. Several things changed while I was writing, including my own voltage floor and my own winner, and I showed that happening rather than quietly restating the conclusion.

Every decision was mine. The two-mile radius, the 230 kV floor, the one-mile gas rule, cutting the expensive states, reading a blank queue as a phone call worth making, picking Mt. Juliet over the better-documented site — I made all of those, some of them badly, and none of them are in any dataset.

That division is the whole product. Substation Scout will tell you what is near a coordinate and where the claim came from. It will not tell you which site is best, because "best" depends on your load, your tariff, your schedule, your cost of capital and your tolerance for a phone call that might go badly. A tool that ranks sites for you is not being helpful; it is hiding somebody else's assumptions inside a number and lending them the authority of a computer.

I'd rather hand you sourced facts and let you be wrong in your own voice. That's what I did here — loudly, and on purpose.

The most useful thing I learned had nothing to do with Costcos. It was how much one screen moves the map. Adding gas didn't refine my list; it relocated it, from the Pacific Northwest to the Southeast, and out of the places where my queue data is strongest. Every requirement you add is also a decision about where you're going to end up looking.

Now let me run off and scrape some TVA data.


Figures from Site Scanner and the Queue Wire, both on this site. Queue data covers PJM, ERCOT and BPA; TVA is not ingested, so no queue figure exists for Mt. Juliet. Gas distances are to EIA's mapped pipeline layer (publisher vintage 2025-12-04), not to surveyed pipe, and say nothing about capacity, pressure or whether service is available. Substation line counts are as published in HIFLD, with source dates from 2014-2015. Middle Tennessee Electric's cooperative status and TVA supply are from its fact sheet, retrieved 2026-10-18. Local moratoria are as recorded in Michael Bommarito's Moratorium Data 2026 (CC-BY-4.0, data as of 2026-09-23; Wilson County record tn-wilson-county-2026), the same dataset behind Appendix B of every Site Scanner report; a recorded moratorium's scope is set by its own text. The site's location inside Mount Juliet city limits is from the Census Geocoder (current vintage), retrieved 2026-10-27. Tennessee county zoning authority is Tenn. Code Ann. § 13-7-101, retrieved 2026-10-27. Industrial rates are EIA Electric Power Monthly Table 5.6.A, July 2026, retrieved 2026-10-18.