October 27, 2026 · By Phil
Project Kirkland Part 2 — The 67% I couldn't check
I narrowed 617 Costcos to 24 plausible data center sites with transmission and gas nearby, then tried to find out what's already queued at their substations.
Part 2: The queue we can't see
Last time I took all 617 Costco warehouses in the lower 48, ran them through Site Scanner, and narrowed them to 41 that sit outside a flood hazard area, within two miles of a 230 kV or better substation, and within a mile of a mapped gas pipeline.
Then I trimmed the list by hand.
First, the part where I use judgment and say so
Anything in a state where industrial power runs more than 50% above the national average comes off, and so does the New York City metro. That takes out California, Massachusetts and New Jersey, plus Brooklyn and Westbury.
For color on this, consider that a data center's operating cost is dominated by energy, and at a 50 MW round-the-clock load you're buying 438 million kilowatt-hours a year. Every cent per kilowatt-hour in a higher rate is $4.4 million a year in energy cost on the 50MW.
For comparing power cost by state*, here's the industrial rate picture for the states on my list, from EIA's July 2026 state table:
| State | Industrial ¢/kWh | 50 MW annual energy bill |
|---|---|---|
| Louisiana | 6.08 | $26.6M |
| Texas | 7.07 | $31.0M |
| Tennessee | 7.13 | $31.2M |
| Oregon | 8.92 | $39.1M |
| Florida | 9.17 | $40.2M |
| Arizona | 9.35 | $41.0M |
| Colorado | 9.54 | $41.8M |
| US average | 9.77 | $42.8M |
| Michigan | 9.81 | $43.0M |
| Nevada | 10.04 | $44.0M |
| Virginia | 10.07 | $44.1M |
| Pennsylvania | 11.04 | $48.4M |
| New Jersey | 15.63 | $68.5M |
| Massachusetts | 20.25 | $88.7M |
| California | 25.11 | $110.0M |
\* Important: These are just industrial figures pulled for the purpose of comparing state averages and don't necessarily represent what a data center is paying.
Removing those seventeen leaves 24 sites.
The obvious next question
Twenty-four sites, each with a big substation and a gas line nearby. So: what's already queued up at those substations?
This is the question that actually determines whether a site is viable. A substation with 500 kV service and no headroom is a picture of a substation. What you want to know is who else is in line, for how much, and how far along they are.
I can answer it for eight of them, and even those 8 have a big caveat since generation requests are published and load requests are not.
Where that leaves the 24
| City | State | Nearest ≥230 kV | Dist | Gas line | Utility | Queue answer |
|---|---|---|---|---|---|---|
| Tempe | AZ | 500 kV — KYRENE | 1.19 mi | 0.28 mi | CITY OF MESA - (AZ) | Not ingested — unknown |
| Pottstown | PA | 500 kV — LIMERICK (500KV SUB) | 1.32 mi | 0.01 mi | PECO ENERGY CO | 5 projects, 1 active |
| Mt. Juliet | TN | 500 kV — WILSON | 1.61 mi | 0.37 mi | MIDDLE TENNESSEE E M C | Covered on paper — not really checked |
| San Antonio | TX | 345 kV — CAGNON ROAD | 1.11 mi | 0.71 mi | CITY OF SAN ANTONIO - (TX) | None found |
| Houston | TX | 345 kV — UNKNOWN302970 | 1.28 mi | 0.18 mi | CENTERPOINT ENERGY | Substation unnamed — unmatchable |
| Arlington | TX | 345 kV — UNKNOWN305459 | 1.68 mi | 0.13 mi | ONCOR ELECTRIC DELIVERY COMPANY LLC | Substation unnamed — unmatchable |
| Lewisville | TX | 345 kV — NORTHWEST CARROLLTON | 1.77 mi | 0.78 mi | TEXAS-NEW MEXICO POWER CO | None found |
| Auburn Hills | MI | 345 kV — UNKNOWN128507 | 1.86 mi | 0.7 mi | DTE ELECTRIC COMPANY | Substation unnamed — unmatchable |
| Richmond | TX | 345 kV — O'BRIEN | 1.9 mi | 0.06 mi | CENTERPOINT ENERGY | 1 project, 1 active |
| Lafayette | LA | 230 kV — FLANDERS | 0.48 mi | 0.47 mi | ENTERGY LOUISIANA LLC | Not ingested — unknown |
| Woodbridge | VA | 230 kV — NOVEC SMOKETOWN | 0.58 mi | 0.48 mi | NORTHERN VIRGINIA ELEC COOP | None found |
| Tampa | FL | 230 kV — SHELDON ROAD | 0.68 mi | 1 mi | TAMPA ELECTRIC CO | Not ingested — unknown |
| North Wales | PA | 230 kV — HARTMAN | 0.91 mi | 0.25 mi | PECO ENERGY CO | 5 projects, none pending |
| Gypsum | CO | 230 kV — COOLEY MESA | 0.95 mi | 0.29 mi | HOLY CROSS ELECTRIC ASSN, INC | Not ingested — unknown |
| Chantilly | VA | 230 kV — UNKNOWN116835 | 0.95 mi | 0.5 mi | VIRGINIA ELECTRIC & POWER CO | Substation unnamed — unmatchable |
| Eugene | OR | 230 kV — MCKENZIE | 1.19 mi | 0.8 mi | EMERALD PEOPLE'S UTILITY DIST | None found |
| Gilbert | AZ | 230 kV — CORBELL | 1.4 mi | 0.67 mi | CITY OF MESA - (AZ) | Not ingested — unknown |
| Richmond | VA | 230 kV — TRABUE | 1.4 mi | 1 mi | VIRGINIA ELECTRIC & POWER CO | 1 project, 0 active |
| Las Vegas | NV | 230 kV — BELTWAY | 1.46 mi | 0.15 mi | NEVADA POWER CO | Not ingested — unknown |
| Leesburg | VA | 230 kV — TAP139243 | 1.5 mi | 0.83 mi | VIRGINIA ELECTRIC & POWER CO | Substation unnamed — unmatchable |
| Denver | CO | 230 kV — CHAMBERS | 1.53 mi | 0.19 mi | PUBLIC SERVICE CO OF COLORADO | Not ingested — unknown |
| Bradenton | FL | 230 kV — UNKNOWN120645 | 1.6 mi | 0.34 mi | FLORIDA POWER & LIGHT CO | Not ingested — unknown |
| Brandon | FL | 230 kV — STATE ROUTE 60 | 1.67 mi | 0.81 mi | TAMPA ELECTRIC CO | Not ingested — unknown |
| Colorado Springs | CO | 230 kV — UNKNOWN202239 | 1.7 mi | 0.68 mi | CITY OF COLORADO SPRINGS - (CO) | Not ingested — unknown |
Count the bold. Sixteen of 24 sites — 67% — return an answer that isn't an answer.
That's worse than the version of this list without gas, and it's worse for a reason. They fail for three different reasons, and the gas screen made the first one much bigger.
Reason one: ten sites in states I don't cover yet
I load interconnection queue data from PJM, ERCOT and BPA — 25 states. Ten of my 24 finalists are in states I don't cover: Arizona, Colorado, Florida, Louisiana and Nevada.
Look at that list of states. Gas pulled my shortlist south and west, toward the Gulf Coast, Florida and the Mountain West, where the pipelines are and where I have no queue data. The gas screen and my coverage map point in opposite directions.
This is a coverage gap, it's mine, and it's on the roadmap. It's also the harder kind. Louisiana is mostly MISO, which publishes a machine-readable queue, so that one is tractable. Florida, Arizona, Colorado and Nevada are mostly non-RTO utilities, each running its own interconnection process and publishing its own way. That's the shape the Pacific Northwest was before I found BPA's queue spreadsheet, times four.
Reason two: the substation has no name
This is the one no amount of ingestion fixes.
Five of my 24 sites are in a covered state but their nearest qualifying substation has no name in the public record: UNKNOWN302970 (Houston), UNKNOWN305459 (Arlington), UNKNOWN116835 (Chantilly), TAP139243 (Leesburg) and UNKNOWN128507 (Auburn Hills). Two more, Bradenton and Colorado Springs, are unnamed too, but they're already counted above.
Those records are fine for screening. They carry a location and a voltage, which is all the funnel in part one needed. But interconnection queue entries identify their point of interconnection by name, as free text, typed by whoever filed the request. So the join between "substation near this Costco" and "projects queued at that substation" is a string match.
No name, no match.
Look at which sites that hits. Chantilly and Leesburg are the two Costcos in the heart of Northern Virginia, the best-known data center market in the world, and they're the two I can't check, because the substations next to them are anonymous in the federal inventory.
Reason three: covered on paper
This one I didn't know about until I wrote this post.
My coverage list is built from the queue rows I've loaded: if any project in a state appears in my data, the state counts as covered. Tennessee counts as covered. So does Michigan.
But Tennessee's rows are five PJM projects in Sullivan, Greene and Hawkins counties, up in the northeast corner of the state. Mt. Juliet is outside Nashville, in TVA country, and TVA's queue isn't in my data. So "None found" at Wilson doesn't mean anybody looked. It means I hadn't looked anywhere near it.
Michigan is the same: PJM's Michigan rows are all in the southwest corner of the state (Berrien, Cass, Van Buren, St. Joseph counties). Auburn Hills is DTE territory north of Detroit, so it would have come back blank even if its substation had a name.
I've marked Mt. Juliet as "covered on paper" in the table rather than "none found." I will be adding more queues to the database, but that this exercise is so fruitless speaks to the problem at hand, the grid is not legible at all.
What the eight answers actually show
Take out all three failure modes and eight sites have real answers. Four come back genuinely empty: San Antonio, Lewisville, Woodbridge and Eugene, with no queue activity found, which is a real finding and not a shrug. It could be taken as an indictator that engineer resources are not being directed at these locations.
The other four have something to look at, and two of those have something active.
Pottstown, Pennsylvania — 1.32 miles from Limerick, which the public data lists as two substations, a 230 kV and a 500 kV. Five distinct projects across both, one active: C01-1055, "Limerick 500 kV," 348 MW, nuclear. The other four are withdrawn — two gas projects at 500 MW and 75 MW, two small nuclear entries.
Pottstown also has the closest mapped gas line on this list: Columbia Gas Transmission, 0.01 miles away, which on a federal map means more or less running past the parking lot.
That withdrawal history is the interesting part, and it cuts both ways. Somebody tried to put 500 MW of gas generation here and didn't finish. Is that evidence the interconnection path is hard, or evidence of a dozen other things — financing, a buyer that walked, a better site? The data does not say.
Richmond, Texas — one active ERCOT project, 24INR0584, "Kegans BESS," 164.6 MW of storage, screening and facilities studies complete, interconnection agreement stage.
North Wales, Pennsylvania — this one is the gas story in miniature. Five projects at the North Wales substation, none of them pending. Two are listed as in service, and both are gas: G22, filed as "Merck," 38 MW, and AE1-221, "West Point Cogeneration Facility." The other three are small diesel entries, two deactivated and one withdrawn. So the queue history at this substation is somebody running their own gas generation. That's the plan B Project Kirkland asked for, already working a few miles up the road.
Richmond, Virginia — one project, AG2-275, a 150 MW battery at the Southwest 230 kV substation, withdrawn.
The caveat that matters most
Three of those four matches are on a different substation than the one that got the site shortlisted.
Pottstown is clean — the queue rows name Limerick, which is what put the site on the list. But North Wales was shortlisted on Hartman at 0.91 miles and the queue match is the North Wales substation, 3.41 miles away. Richmond, Virginia was shortlisted on Trabue at 1.4 miles; the match is Southwest, 4.08 miles out. Richmond, Texas was shortlisted on O'Brien at 1.9 miles; the match is Clodine, a 138 kV substation 5.42 miles away.
So "this site has queue activity nearby" is doing a lot of work in that sentence. The activity is near the site, not necessarily at the substation that made the site attractive. If you were actually evaluating these, that distinction is the difference between a relevant constraint and a fun fact.
I'm flagging it because it's exactly the kind of thing a ranked score would have flattened into a number.
The honest scoreboard
Twenty-four plausible sites. Four with any queue signal, two with anything pending, four genuinely empty, five with an anonymous substation, ten waiting on ingestion work I haven't done, and one I thought I'd checked and hadn't.
Adding gas made the list better for the client and worse for me. The pipelines run through Texas, Louisiana, Florida and the Mountain West, and my queue data is strongest in the Mid-Atlantic and the Pacific Northwest. Every screen you add drags the shortlist somewhere, and you should know where it's dragging it before you trust what comes back.
The useful thing I learned writing this one wasn't about Costcos. It was that my own "covered" flag was overstating what I know. That's the same lesson as BPA's spreadsheet, from the other side: the hard part of public data is usually not getting it, it's being honest about where it stops.
Next: I introduce some criteria I've been deliberately withholding, argue with myself about Pottstown versus a co-op outside Nashville, and pick a winner on grounds I'll cheerfully admit are made up.
Read on: Part 3 — Picking a winner, badly
Every queue figure here came from Site Scanner and the Queue Wire, both on this site. Queue data covers PJM, ERCOT and BPA; ERCOT publishes monthly and can lag the live queue by about 30 days. Absence of a project is not evidence that none exists. Queue statuses are reproduced as filed. Gas distances are to EIA's mapped pipeline layer (publisher vintage 2025-12-04), not to surveyed pipe, and say nothing about capacity or service. Industrial electricity rates are from EIA Electric Power Monthly Table 5.6.A, July 2026 data, retrieved 2026-10-18 — state averages across all industrial customers, not a tariff quote for a specific site.