Substation Scout

Tap TRIBUTE4A - REDCREEK4A substation interconnection queue

2 active projects totalling 402 MW in the ERCOT queue.

2active projects
402active MW
2total filed
Queue IDProjectkVMWResourceStatus
25INR0853 Tango Lily BESS 138 201 Battery SS Completed, FIS Started, No IA
29INR0231 Tango Lily Solar 138 201 Solar SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.