Tap Stryker to Martin Lake substation interconnection queue

2 active projects totalling 235.6 MW in the ERCOT queue.

2active projects
235.6active MW
2total filed
Queue IDProjectkVMWResourceStatus
25INR0591 Zeus Rusk BESS 345 208.8 Battery SS Completed, FIS Started, No IA
25INR0590 Zeus Rusk Solar 345 26.8 Solar SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.