Tap Schroeder - Big Oak substation interconnection queue
2 active projects totalling 132.6 MW in the ERCOT queue.
2active projects
132.6active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 27INR0248 | Double A Solar SLF | 69 | 132.6 | Solar | SS Completed, FIS Started, No IA |
| 27INR0257 | Double A Storage SLF | 69 | 0 | Battery | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.