Tap North Edinburg - Stewart Road substation interconnection queue
2 active projects totalling 419.9 MW in the ERCOT queue.
2active projects
419.9active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 24INR0102 | Val Vista Grid BESS 2 | 345 | 210.6 | Battery | SS Completed, FIS Started, IA |
| 22INR0387 | Val Vista Grid BESS 1 | 345 | 209.3 | Battery | SS Completed, FIS Started, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.