Tap Cenizo - Cruce Ckt-1 substation interconnection queue
2 active projects totalling 845.2 MW in the ERCOT queue.
2active projects
845.2active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 28INR0072 | Mirando Valley Wind | 345 | 478.7 | Wind | SS Completed, FIS Started, IA |
| 28INR0434 | Viento Bravo Wind | 345 | 366.5 | Wind | SS Completed, FIS Started, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.