Substation Scout

Tap 138-kV Weimar () to Schulenburg () substation interconnection queue

2 active projects totalling 200 MW in the ERCOT queue.

2active projects
200active MW
2total filed
Queue IDProjectkVMWResourceStatus
30INR0045 Radiant Plains Energy Center BESS n/r 100 Battery SS Completed, FIS Started, No IA
32INR0002 Radiant Plains Energy Center Solar n/r 100 Solar SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.