Sand_Bluff () substation interconnection queue

2 active projects totalling 248.1 MW in the ERCOT queue.

2active projects
248.1active MW
2total filed
Queue IDProjectkVMWResourceStatus
26INR0452 Cannibal Draw Solar 345 149.5 Solar SS Completed, FIS Started, IA
26INR0453 Cannibal Draw Storage 345 98.6 Battery SS Completed, FIS Started, IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.