# ILLN4A substation interconnection queue
2 active projects totalling 154.1 MW in the ERCOT queue.
2active projects
154.1active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 26INR0365 | BLACK BEAR SOLAR | 138 | 102.9 | Solar | SS Completed, FIS Started, No IA |
| 26INR0366 | BLACK BEAR BESS | 138 | 51.2 | Battery | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.