Divide (#) to Sand Bluff Wind Farm (#) substation interconnection queue

2 active projects totalling 411.8 MW in the ERCOT queue.

2active projects
411.8active MW
2total filed
Queue IDProjectkVMWResourceStatus
29INR0185 Roan Solar Phase 1 345 205.9 Solar SS Completed, FIS Started, No IA
29INR0187 Roan Solar Phase 2 345 205.9 Solar SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.