Divide (#) to Sand Bluff Wind Farm (#) substation interconnection queue
2 active projects totalling 411.8 MW in the ERCOT queue.
2active projects
411.8active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 29INR0185 | Roan Solar Phase 1 | 345 | 205.9 | Solar | SS Completed, FIS Started, No IA |
| 29INR0187 | Roan Solar Phase 2 | 345 | 205.9 | Solar | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.