Braunig substation interconnection queue

2 active projects totalling 34.5 MW in the ERCOT queue.

2active projects
34.5active MW
2total filed
Queue IDProjectkVMWResourceStatus
25INR0531 CPS Energy AvR1CT2 Rotor Replacement 345 23.2 Gas SS Completed, FIS Completed, No IA
24INR0427 CPS AvR CT1 Rotor Replacement 345 11.3 Gas SS Completed, FIS Completed, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.