Baez substation interconnection queue

2 active projects totalling 177.6 MW in the ERCOT queue.

2active projects
177.6active MW
2total filed
Queue IDProjectkVMWResourceStatus
26INR0134 Myers Solar 69 101.6 Solar SS Completed, FIS Started, No IA
26INR0135 Myers Storage 69 76 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.