Adamsville substation interconnection queue

2 active projects totalling 310.5 MW in the ERCOT queue.

2active projects
310.5active MW
2total filed
Queue IDProjectkVMWResourceStatus
30INR0037 Solgen Solar 138 160.2 Solar SS Completed, FIS Started, No IA
30INR0038 Solgen Storage 138 150.3 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.