Bullock Gas (33INR0005) is listed in the ERCOT interconnection queue as a 1,400 MW gas project in Hill County, TX. The filing names BULLOCK STATION (Bus# ) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of July 1, 2032. It records the screening study as complete on July 29, 2026.

Queue ID33INR0005
Project nameBullock Gas
Status (as published)SS Completed, FIS Started, No IA
SubstationBULLOCK STATION (Bus# )
Point of interconnectionBULLOCK 345 KV STATION (Bus# 68096)
CountyHill
StateTX
Voltage345 kV
Capacity1,400 MW
Resource (as published)GAS/CC
Resource categoryGas (normalized for filtering)
Target commercial operation2032-07-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Hill, TX: 27 requests in the ERCOT queue, 23 active totaling 7,894.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityBullock Data Center, LLC
CDR reporting zoneNORTH
Fuel codeGAS
Technology codeCC
Screening study complete2026-07-29

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first