Substation Scout

BM Freestone Energy Center

ERCOT queue ID 29INR0298

BM Freestone Energy Center (29INR0298) is listed in the ERCOT interconnection queue as a 990.6 MW gas project in Freestone County, TX. The filing names Loop Big Brown E to Navarro Ckt 1(PTI#-) and Big Brown W to Tarantulla Ckt 1 (PTI#-) at 31.° -96.° as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 20, 2029. It records the screening study as complete on May 21, 2026.

Queue ID29INR0298
Project nameBM Freestone Energy Center
Status (as published)SS Completed, FIS Started, No IA
SubstationLoop Big Brown E to Navarro Ckt 1(PTI#-) and Big Brown W to Tarantulla Ckt 1 (PTI#-) at 31.° -96.°
Point of interconnectionLoop Big Brown E to Navarro Ckt 1(PTI#3380-68091) and Big Brown W to Tarantulla Ckt 1 (PTI#3381-3344) at 31.813367° -96.147730°
CountyFreestone
StateTX
VoltageNot reported
Capacity990.6 MW
Resource (as published)GAS/CC
Resource categoryGas (normalized for filtering)
Target commercial operation2029-09-20
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Freestone, TX: 24 requests in the ERCOT queue, 24 active totaling 7,337.8 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityBlack Mountain Energy Storage II
CDR reporting zoneNORTH
Fuel codeGAS
Technology codeCC
Screening study complete2026-05-21

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.