ERCOT queue ID 29INR0218

Kickstart Energy Storage VI (29INR0218) is listed in the ERCOT interconnection queue as a 1,026.2 MW battery project in Ellis County, TX. The filing names Venus to Navarro as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2029. It records the screening study as complete on February 23, 2026.

Queue ID29INR0218
Project nameKickstart Energy Storage VI
Status (as published)SS Completed, FIS Started, No IA
SubstationVenus to Navarro
Point of interconnection345 KV Venus 1907 to Navarro 68091
CountyEllis
StateTX
Voltage345 kV
Capacity1,026.2 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-12-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Ellis, TX: 30 requests in the ERCOT queue, 26 active totaling 5,761.2 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityKickstart Infrastructure LLC
CDR reporting zoneNORTH
Fuel codeOTH
Technology codeBA
Screening study complete2026-02-23

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first