Alila BESS II
ERCOT queue ID 29INR0207
Alila BESS II (29INR0207) is listed in the ERCOT interconnection queue as a 205.7 MW battery project in San Patricio County, TX. The filing names Angstrom as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of January 25, 2029. It records the screening study as complete on April 6, 2026.
| Queue ID | 29INR0207 |
|---|---|
| Project name | Alila BESS II |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Angstrom |
| Point of interconnection | 8249 Angstrom 345kV |
| County | San Patricio |
| State | TX |
| Voltage | 345 kV |
| Capacity | 205.7 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2029-01-25 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
San Patricio, TX: 28 requests in the ERCOT queue, 27 active totaling 6,857.5 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Electra Energy Project, LLC |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2026-04-06 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.