Falcon BESS
ERCOT queue ID 29INR0169
| Queue ID | 29INR0169 |
|---|---|
| Project name | Falcon BESS |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap # CENIZO to # DEL SOL |
| Point of interconnection | Tap 345kV #80225 CENIZO to #80307 DEL SOL |
| County | Zapata |
| State | TX |
| Voltage | 345 kV |
| Capacity | 516.7 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2029-12-01 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Falcon Energy Project, LLC |
|---|---|
| Cdr Zone | SOUTH |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 45958 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.