NRG Prairie Energy Center
ERCOT queue ID 29INR0158
NRG Prairie Energy Center (29INR0158) is listed in the ERCOT interconnection queue as a 1,253 MW gas project in Hill County, TX. The filing names Tap # Venus Switch – # Fort Smith Switch as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2030. It records the screening study as complete on June 30, 2026.
| Queue ID | 29INR0158 |
|---|---|
| Project name | NRG Prairie Energy Center |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap # Venus Switch – # Fort Smith Switch |
| Point of interconnection | Tap #1907 Venus Switch – #3389 Fort Smith Switch 345 kV |
| County | Hill |
| State | TX |
| Voltage | 345 kV |
| Capacity | 1,253 MW |
| Resource (as published) | GAS/CC |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2030-12-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Hill, TX: 27 requests in the ERCOT queue, 23 active totaling 7,894.6 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | NRG Prairie Energy Center LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | GAS |
| Technology code | CC |
| Screening study complete | 2026-06-30 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.