MilamStation Power Secured Gas Generation
ERCOT queue ID 29INR0120
MilamStation Power Secured Gas Generation (29INR0120) is listed in the ERCOT interconnection queue as a 846 MW gas project in Milam County, TX. The filing names Little Pond Switch (Bus #) – Hog Creek Switch (Bus #) Line as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 25, 2029. It records the screening study as complete on June 19, 2025.
| Queue ID | 29INR0120 |
|---|---|
| Project name | MilamStation Power Secured Gas Generation |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Little Pond Switch (Bus #) – Hog Creek Switch (Bus #) Line |
| Point of interconnection | Little Pond Switch (Bus #3377) – Hog Creek Switch (Bus #3704) 345 kV Line |
| County | Milam |
| State | TX |
| Voltage | 345 kV |
| Capacity | 846 MW |
| Resource (as published) | GAS/CC |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2029-09-25 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Milam, TX: 35 requests in the ERCOT queue, 30 active totaling 8,525.6 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | LCC-TX8, LLC |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | GAS |
| Technology code | CC |
| Screening study complete | 2025-06-19 |