Fluvanna Max Solar SLF
ERCOT queue ID 29INR0077
Fluvanna Max Solar SLF (29INR0077) is listed in the ERCOT interconnection queue as a 152.7 MW solar project in Scurry County, TX. The filing names DERMOTT as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 14, 2029. It records the screening study as complete on March 18, 2025.
| Queue ID | 29INR0077 |
|---|---|
| Project name | Fluvanna Max Solar SLF |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | DERMOTT |
| Point of interconnection | 11305 DERMOTT 345 kV |
| County | Scurry |
| State | TX |
| Voltage | 345 kV |
| Capacity | 152.7 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2029-09-14 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
DERMOTT substation: 2 requests in the ERCOT queue, 2 active totaling 204.5 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 28INR0202 | Fluvanna Max BESS SLF | 51.8 | Battery | SS Completed, FIS Started, No IA |
Scurry, TX: 23 requests in the ERCOT queue, 17 active totaling 5,057.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Fluvanna Max Solar LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | SOL |
| Technology code | PV |
| Screening study complete | 2025-03-18 |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.