Fluvanna Max Solar SLF (29INR0077) is listed in the ERCOT interconnection queue as a 152.7 MW solar project in Scurry County, TX. The filing names DERMOTT as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 14, 2029. It records the screening study as complete on March 18, 2025.

Queue ID29INR0077
Project nameFluvanna Max Solar SLF
Status (as published)SS Completed, FIS Started, No IA
SubstationDERMOTT
Point of interconnection11305 DERMOTT 345 kV
CountyScurry
StateTX
Voltage345 kV
Capacity152.7 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2029-09-14
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

DERMOTT substation: 2 requests in the ERCOT queue, 2 active totaling 204.5 MW.

Queue IDProjectMWResourceStatus
28INR0202Fluvanna Max BESS SLF51.8BatterySS Completed, FIS Started, No IA

Scurry, TX: 23 requests in the ERCOT queue, 17 active totaling 5,057.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityFluvanna Max Solar LLC
CDR reporting zoneWEST
Fuel codeSOL
Technology codePV
Screening study complete2025-03-18
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first