ERCOT queue ID 29INR0063

Columbine Wind (29INR0063) is listed in the ERCOT interconnection queue as a 295 MW wind project in Gonzales County, TX. The filing names TAP BUS # SHAULA- BUS # ELM CREEK as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 1, 2029. It records the screening study as complete on May 20, 2025.

Queue ID29INR0063
Project nameColumbine Wind
Status (as published)SS Completed, FIS Started, No IA
SubstationTAP BUS # SHAULA- BUS # ELM CREEK
Point of interconnectionTAP 345KV BUS #5380 SHAULA- BUS #5133 ELM CREEK
CountyGonzales
StateTX
Voltage345 kV
Capacity295 MW
Resource (as published)WIN/WT
Resource categoryWind (normalized for filtering)
Target commercial operation2029-09-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Gonzales, TX: 8 requests in the ERCOT queue, 7 active totaling 1,171.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityWilson Wind LLC
CDR reporting zoneSOUTH
Fuel codeWIN
Technology codeWT
Screening study complete2025-05-20
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first