Old Alma Road Solar (28INR0495) is listed in the ERCOT interconnection queue as a 20.1 MW solar project in Ellis County, TX. The filing names ENNS_SE_8 as its point of interconnection. ERCOT lists its status as “SS Started, FIS Started, No IA”, with a target commercial operation date of October 31, 2028.

Queue ID28INR0495
Project nameOld Alma Road Solar
Status (as published)SS Started, FIS Started, No IA
SubstationENNS_SE_8
Point of interconnection2326 ENNS_SE_8 138kV
CountyEllis
StateTX
Voltage138 kV
Capacity20.1 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2028-10-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Ellis, TX: 30 requests in the ERCOT queue, 26 active totaling 5,761.2 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityWildcat Renewables, LLC
CDR reporting zoneNORTH
Fuel codeSOL
Technology codePV
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.