Vista Bluff Wind II "Alternate POI"

ERCOT queue ID 28INR0447

Vista Bluff Wind II "Alternate POI" (28INR0447) is listed in the ERCOT interconnection queue as a 290.4 MW wind project in Upton County, TX. The filing names tap North McCamey - Bearkat (Benedum station that LCRA will build part of 24RPG024). as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2029. It records the screening study as complete on December 12, 2025.

Queue ID28INR0447
Project nameVista Bluff Wind II "Alternate POI"
Status (as published)SS Completed, FIS Started, No IA
Substationtap North McCamey - Bearkat (Benedum station that LCRA will build part of 24RPG024).
Point of interconnectiontap 345 kV (76000) North McCamey - (59903) Bearkat (Benedum 345 kV station that LCRA will build part of 24RPG024).
CountyUpton
StateTX
Voltage345 kV
Capacity290.4 MW
Resource (as published)WIN/WT
Resource categoryWind (normalized for filtering)
Target commercial operation2029-12-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Upton, TX: 22 requests in the ERCOT queue, 18 active totaling 5,611.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityVista Bluff Windpower, LLC
CDR reporting zoneWEST
Fuel codeWIN
Technology codeWT
Screening study complete2025-12-12
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.