Substation Scout

Blue Spring Solar

ERCOT queue ID 28INR0433

Queue ID28INR0433
Project nameBlue Spring Solar
Status (as published)SS Completed, FIS Started, No IA
Substation# Clear Crossing
Point of interconnection#60515 Clear Crossing 345 kV
CountyHaskell
StateTX
Voltage345 kV
Capacity301 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-10-28
Source datasetlarge

Additional filed fields

Interconnecting EntityFlat Creek Solar, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete45975
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.