Reunion Storage

ERCOT queue ID 28INR0333

Reunion Storage (28INR0333) is listed in the ERCOT interconnection queue as a 200.3 MW battery project in Wilbarger County, TX. The filing names Tap # Tesla Road to # Riley as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of July 1, 2028. It records the screening study as complete on June 19, 2025.

Queue ID28INR0333
Project nameReunion Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationTap # Tesla Road to # Riley
Point of interconnectionTap 345kV #60504 Tesla Road to #6111 Riley
CountyWilbarger
StateTX
Voltage345 kV
Capacity200.3 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-07-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap # Tesla Road to # Riley substation: 2 requests in the ERCOT queue, 2 active totaling 801.2 MW.

Queue IDProjectMWResourceStatus
28INR0332Reunion Solar600.9SolarSS Completed, FIS Started, No IA

Wilbarger, TX: 24 requests in the ERCOT queue, 21 active totaling 8,450.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityReunion Solar, LLC
CDR reporting zoneWEST
Fuel codeOTH
Technology codeBA
Screening study complete2025-06-19

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.