Magnet Storage
ERCOT queue ID 28INR0298
Magnet Storage (28INR0298) is listed in the ERCOT interconnection queue as a 426.7 MW battery project in Borden County, TX. The filing names Faraday Substation (#) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 29, 2029. It records the screening study as complete on October 22, 2025.
| Queue ID | 28INR0298 |
|---|---|
| Project name | Magnet Storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Faraday Substation (#) |
| Point of interconnection | Faraday 345 kV Substation (#59905) |
| County | Borden |
| State | TX |
| Voltage | 345 kV |
| Capacity | 426.7 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2029-09-29 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Borden, TX: 19 requests in the ERCOT queue, 17 active totaling 5,556.7 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | HyFuels Big Spring LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2025-10-22 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.