Substation Scout

Dempsey Storage SLF

ERCOT queue ID 28INR0238

Dempsey Storage SLF (28INR0238) is listed in the ERCOT interconnection queue as a battery request filed at 0 MW (a net change or energy-only filing) in Leon County, TX. The filing names Tap the Ridge (#37)-Robertson (#32) line; BEPC as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 8, 2028. It records the screening study as complete on May 20, 2025.

Queue ID28INR0238
Project nameDempsey Storage SLF
Status (as published)SS Completed, FIS Started, No IA
SubstationTap the Ridge (#37)-Robertson (#32) line; BEPC
Point of interconnectionTap the 138 KV Ridge (#37)-Robertson (#32) line; BEPC
CountyLeon
StateTX
Voltage138 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-09-08
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Leon, TX: 14 requests in the ERCOT queue, 13 active totaling 6,147.5 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityDempsey Storage LLC
CDR reporting zoneNORTH
Fuel codeOTH
Technology codeBA
Screening study complete2025-05-20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.