Gail Mountain Solar

ERCOT queue ID 28INR0176

Gail Mountain Solar (28INR0176) is listed in the ERCOT interconnection queue as a 244.4 MW solar project in Borden County, TX. The filing names Muleshoe (Bus #) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of August 25, 2028. It records the screening study as complete on January 14, 2025 and the interconnection agreement as signed on December 30, 2025.

Queue ID28INR0176
Project nameGail Mountain Solar
Status (as published)SS Completed, FIS Started, IA
SubstationMuleshoe (Bus #)
Point of interconnectionMuleshoe (Bus #59922) 345 kV
CountyBorden
StateTX
Voltage345 kV
Capacity244.4 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2028-08-25
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Borden, TX: 19 requests in the ERCOT queue, 17 active totaling 5,556.7 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityGail Mountain Solar, LLC
CDR reporting zoneWEST
Fuel codeSOL
Technology codePV
Interconnection agreement signed2025-12-30
Screening study complete2025-01-14
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first