Alpujarra Solar

ERCOT queue ID 28INR0068

Queue ID28INR0068
Project nameAlpujarra Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationGALOW
Point of interconnection5521 GALOW 138 KV
CountyWharton
StateTX
Voltage138 kV
Capacity112.5 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-05-01
Source datasetlarge

Additional filed fields

Interconnecting EntityGreening USA Corp.
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45623
Water AvailabilityNot Required