Windecker (28INR0057) is listed in the ERCOT interconnection queue as a 419.7 MW wind project in Upton County, TX. The filing names Catclaw Switch as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of April 17, 2028. It records the screening study as complete on June 19, 2024.

Queue ID28INR0057
Project nameWindecker
Status (as published)SS Completed, FIS Started, No IA
SubstationCatclaw Switch
Point of interconnection10058 Catclaw Switch 138kV
CountyUpton
StateTX
Voltage138 kV
Capacity419.7 MW
Resource (as published)WIN/WT
Resource categoryWind (normalized for filtering)
Target commercial operation2028-04-17
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Upton, TX: 22 requests in the ERCOT queue, 18 active totaling 5,611.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityWindecker Energy LLC
CDR reporting zoneWEST
Fuel codeWIN
Technology codeWT
Screening study complete2024-06-19
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first