Substation Scout

Freestone Battery Storage Project

ERCOT queue ID 28INR0055

Freestone Battery Storage Project (28INR0055) is listed in the ERCOT interconnection queue as a 210.5 MW battery project in Freestone County, TX. The filing names RICHLAND CHAMBERS (PSS/E Bus Name: RICHLND1_5) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 16, 2028. It records the screening study as complete on April 30, 2024.

Queue ID28INR0055
Project nameFreestone Battery Storage Project
Status (as published)SS Completed, FIS Started, No IA
SubstationRICHLAND CHAMBERS (PSS/E Bus Name: RICHLND1_5)
Point of interconnection3134 RICHLAND CHAMBERS 345kV (PSS/E Bus Name: RICHLND1_5)
CountyFreestone
StateTX
Voltage345 kV
Capacity210.5 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-12-16
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Freestone, TX: 24 requests in the ERCOT queue, 24 active totaling 7,337.8 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityFreestone Power Generation, LLC
CDR reporting zoneNORTH
Fuel codeOTH
Technology codeBA
Screening study complete2024-04-30

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.