Substation Scout

Draco Solar

ERCOT queue ID 27INR0499

Draco Solar (27INR0499) is listed in the ERCOT interconnection queue as a 500 MW solar project in Borden County, TX. The filing names Tap Long Draw – Faraday CKT 1 and LONGDRAW - GALVANI CKT 2 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of August 19, 2027. It records the screening study as complete on July 19, 2025.

Queue ID27INR0499
Project nameDraco Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Long Draw – Faraday CKT 1 and LONGDRAW - GALVANI CKT 2
Point of interconnectionTap Long Draw (59900) – Faraday (59905) CKT 1 and LONGDRAW (59900) - GALVANI(59912) CKT 2
CountyBorden
StateTX
VoltageNot reported
Capacity500 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2027-08-19
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Borden, TX: 19 requests in the ERCOT queue, 17 active totaling 5,556.7 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityDraco Solar LLC
CDR reporting zoneWEST
Fuel codeSOL
Technology codePV
Screening study complete2025-07-19
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.