Elk Unit 4

ERCOT queue ID 27INR0181

Queue ID27INR0181
Project nameElk Unit 4
Status (as published)SS Completed, FIS Completed, IA
SubstationAEEC_5
Point of interconnection141607 AEEC_5
CountyHale
StateTX
VoltageNot reported
Capacity210 MW
Resource (as published)GAS/GT
Resource categoryGas (normalised for filtering)
Target commercial operation2027-02-28
Source datasetlarge

Additional filed fields

Interconnecting EntityGolden Spread Electric Cooperative, Inc.
Cdr ZonePANHANDLE
Fuel CodeGAS
Technology CodeGT
Ia Signed46021
Screening Study Complete45478
Fis Approved45854
Air Permit45883
Water Availability46232

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.