Solar Star Rhome Storage
ERCOT queue ID 27INR0040
Solar Star Rhome Storage (27INR0040) is listed in the ERCOT interconnection queue as a 226.2 MW battery project in Wise County, TX. The filing names 576 RHOME as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, No IA”, with a target commercial operation date of September 27, 2029. It records the screening study as complete on July 12, 2023 and the full interconnection study as approved on July 21, 2025.
| Queue ID | 27INR0040 |
|---|---|
| Project name | Solar Star Rhome Storage |
| Status (as published) | SS Completed, FIS Completed, No IA |
| Substation | 576 RHOME |
| Point of interconnection | 576 RHOME 138kV |
| County | Wise |
| State | TX |
| Voltage | 138 kV |
| Capacity | 226.2 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2029-09-27 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Wise, TX: 11 requests in the ERCOT queue, 10 active totaling 3,798 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Solar Star Rhome Storage |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2023-07-12 |
| Full interconnection study approved | 2025-07-21 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.