Sorghum BESS (26INR0474) is listed in the ERCOT interconnection queue as a 208.9 MW battery project in Wharton County, TX. The filing names # Blue Substation as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of December 1, 2027. It records the screening study as complete on July 5, 2024, the full interconnection study as approved on November 13, 2024 and the interconnection agreement as signed on January 8, 2025.
| Queue ID | 26INR0474 |
|---|---|
| Project name | Sorghum BESS |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | # Blue Substation |
| Point of interconnection | #44060 Blue Substation 345kV |
| County | Wharton |
| State | TX |
| Voltage | 345 kV |
| Capacity | 208.9 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2027-12-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Wharton, TX: 44 requests in the ERCOT queue, 42 active totaling 8,624.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Blue Creek BESS, LLC |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2025-01-08 |
| Screening study complete | 2024-07-05 |
| Full interconnection study approved | 2024-11-13 |
| Air permit | Not Required |