Blackcat Storage
ERCOT queue ID 26INR0376
Blackcat Storage (26INR0376) is listed in the ERCOT interconnection queue as a 200.6 MW battery project in Matagorda County, TX. The filing names Blackcat Substation (#) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2027. It records the screening study as complete on April 8, 2024.
| Queue ID | 26INR0376 |
|---|---|
| Project name | Blackcat Storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Blackcat Substation (#) |
| Point of interconnection | 138kV Blackcat Substation (#80124) |
| County | Matagorda |
| State | TX |
| Voltage | 138 kV |
| Capacity | 200.6 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2027-12-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Matagorda, TX: 30 requests in the ERCOT queue, 23 active totaling 5,513.1 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Matagorda ESS, LLC |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2024-04-08 |
| Air permit | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.