Blackcat Storage (26INR0376) is listed in the ERCOT interconnection queue as a 200.6 MW battery project in Matagorda County, TX. The filing names Blackcat Substation (#) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2027. It records the screening study as complete on April 8, 2024.

Queue ID26INR0376
Project nameBlackcat Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationBlackcat Substation (#)
Point of interconnection138kV Blackcat Substation (#80124)
CountyMatagorda
StateTX
Voltage138 kV
Capacity200.6 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2027-12-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Matagorda, TX: 30 requests in the ERCOT queue, 23 active totaling 5,513.1 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityMatagorda ESS, LLC
CDR reporting zoneCOASTAL
Fuel codeOTH
Technology codeBA
Screening study complete2024-04-08
Air permitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first