Edens Solar (26INR0313) is listed in the ERCOT interconnection queue as a 70.8 MW solar project in Hill County, TX. The filing names Tap Itasca - Hillsboro as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of April 9, 2028. It records the screening study as complete on January 22, 2024.
| Queue ID | 26INR0313 |
|---|---|
| Project name | Edens Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap Itasca - Hillsboro |
| Point of interconnection | Tap 69kV 3532 Itasca - 3523 Hillsboro |
| County | Hill |
| State | TX |
| Voltage | 69 kV |
| Capacity | 70.8 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-04-09 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Hill, TX: 27 requests in the ERCOT queue, 23 active totaling 7,894.6 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Hill PV, LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | SOL |
| Technology code | PV |
| Screening study complete | 2024-01-22 |
| Water availability | Not Required |