Substation Scout

Nautilus Heavy Storage

ERCOT queue ID 26INR0306

Nautilus Heavy Storage (26INR0306) is listed in the ERCOT interconnection queue as a 256.2 MW battery project in San Patricio County, TX. The filing names Dupont as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of January 30, 2030. It records the screening study as complete on March 15, 2024.

Queue ID26INR0306
Project nameNautilus Heavy Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationDupont
Point of interconnection8422 Dupont 138kV
CountySan Patricio
StateTX
Voltage138 kV
Capacity256.2 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2030-01-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

San Patricio, TX: 28 requests in the ERCOT queue, 27 active totaling 6,857.5 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityNautilus Heavy Storage, LLC
CDR reporting zoneCOASTAL
Fuel codeOTH
Technology codeBA
Screening study complete2024-03-15

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.