Longleaf Power Station
ERCOT queue ID 26INR0294
| Queue ID | 26INR0294 |
|---|---|
| Project name | Longleaf Power Station |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Redland Substation (# ) |
| Point of interconnection | Redland Substation (# 3321) |
| County | Angelina |
| State | TX |
| Voltage | Not reported |
| Capacity | 600 MW |
| Resource (as published) | GAS/GT |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2029-03-31 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | WattBridge Texas Holdings, LLC |
|---|---|
| Cdr Zone | NORTH |
| Fuel Code | GAS |
| Technology Code | GT |
| Screening Study Complete | 45300 |
| Air Permit | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.