Cold Creek Solar 2
ERCOT queue ID 26INR0290
| Queue ID | 26INR0290 |
|---|---|
| Project name | Cold Creek Solar 2 |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Tap line Big Hill (#) - Twin Buttes (#) |
| Point of interconnection | Tap 345kV line Big Hill (#76003) - Twin Buttes (#76009) |
| County | Schleicher |
| State | TX |
| Voltage | 345 kV |
| Capacity | 431.9 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2028-05-28 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Cold Creek Solar and Storage LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | SOL |
| Technology Code | PV |
| Ia Signed | 45770 |
| Screening Study Complete | 45352 |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.