JackGard BESS (26INR0215) is listed in the ERCOT interconnection queue as a 200.6 MW battery project in Jack County, TX. The filing names Jacksboro as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, No IA”, with a target commercial operation date of April 17, 2029. It records the screening study as complete on November 2, 2023 and the full interconnection study as approved on November 15, 2024.

Queue ID26INR0215
Project nameJackGard BESS
Status (as published)SS Completed, FIS Completed, No IA
SubstationJacksboro
Point of interconnection1429 Jacksboro 345kV
CountyJack
StateTX
Voltage345 kV
Capacity200.6 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-04-17
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Jack, TX: 18 requests in the ERCOT queue, 17 active totaling 7,978.1 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityJackgard BESS
CDR reporting zoneNORTH
Fuel codeOTH
Technology codeBA
Screening study complete2023-11-02
Full interconnection study approved2024-11-15

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first