Arc Energy Storage
ERCOT queue ID 26INR0184
Arc Energy Storage (26INR0184) is listed in the ERCOT interconnection queue as a 204.5 MW battery project in Lamar County, TX. The filing names Tap Paris Switch - ENLOE T8 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, No IA”, with a target commercial operation date of June 30, 2028. It records the screening study as complete on October 27, 2023 and the full interconnection study as approved on May 2, 2025.
| Queue ID | 26INR0184 |
|---|---|
| Project name | Arc Energy Storage |
| Status (as published) | SS Completed, FIS Completed, No IA |
| Substation | Tap Paris Switch - ENLOE T8 |
| Point of interconnection | Tap 138kV 1693 Paris Switch - 11806 ENLOE T8 |
| County | Lamar |
| State | TX |
| Voltage | 138 kV |
| Capacity | 204.5 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-06-30 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Lamar, TX: 28 requests in the ERCOT queue, 25 active totaling 6,189.8 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Paris Energy Storage, LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2023-10-27 |
| Full interconnection study approved | 2025-05-02 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.