Proving Ground Solar
ERCOT queue ID 26INR0150
| Queue ID | 26INR0150 |
|---|---|
| Project name | Proving Ground Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap Live Oak () - Santiago () |
| Point of interconnection | Tap 138 kV Live Oak (6500) - Santiago (6490) |
| County | Schleicher |
| State | TX |
| Voltage | 138 kV |
| Capacity | 82.1 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2028-06-30 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Lantana Solar LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | SOL |
| Technology Code | PV |
| Screening Study Complete | 45204 |
| Air Permit | Not Required |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.