Falcon Zapata Storage 138

ERCOT queue ID 26INR0116

Falcon Zapata Storage 138 (26INR0116) is listed in the ERCOT interconnection queue as a 200.8 MW battery project in Zapata County, TX. The filing names Tap Zapata - Lopeno as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of March 11, 2028. It records the screening study as complete on August 11, 2023 and the interconnection agreement as signed on February 3, 2026.

Queue ID26INR0116
Project nameFalcon Zapata Storage 138
Status (as published)SS Completed, FIS Started, IA
SubstationTap Zapata - Lopeno
Point of interconnectionTap 138kV 8299 Zapata - 8957 Lopeno
CountyZapata
StateTX
Voltage138 kV
Capacity200.8 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-03-11
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Zapata, TX: 28 requests in the ERCOT queue, 27 active totaling 6,291.1 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityFalcon BESS, LLC
CDR reporting zoneSOUTH
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2026-02-03
Screening study complete2023-08-11

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.