Freedom Falcon BESS (26INR0107) is listed in the ERCOT interconnection queue as a 501.9 MW battery project in Zapata County, TX. The filing names Tap # Tiempo - # Rapido as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of August 11, 2028. It records the screening study as complete on September 22, 2023.

Queue ID26INR0107
Project nameFreedom Falcon BESS
Status (as published)SS Completed, FIS Started, No IA
SubstationTap # Tiempo - # Rapido
Point of interconnectionTap 345kV #80224 Tiempo - #80227 Rapido
CountyZapata
StateTX
Voltage345 kV
Capacity501.9 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-08-11
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Zapata, TX: 28 requests in the ERCOT queue, 27 active totaling 6,291.1 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityFalcon BESS, LLC
CDR reporting zoneSOUTH
Fuel codeOTH
Technology codeBA
Screening study complete2023-09-22

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first