Leon Solar Park

ERCOT queue ID 26INR0023

Queue ID26INR0023
Project nameLeon Solar Park
Status (as published)SS Completed, FIS Completed, IA
SubstationTap Grapeland Magnolia Tap (bus #) to Pleasant Springs POI (bus# ) section of the Jewett -Crockett Line
Point of interconnectionTap 138kV Grapeland Magnolia Tap (bus #3355) to Pleasant Springs POI (bus# 3357) section of the Jewett -Crockett 138kV Line
CountyLeon
StateTX
Voltage138 kV
Capacity210.1 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2026-07-01
Source datasetlarge

Additional filed fields

Interconnecting EntityMisae Solar IV LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Ia Signed45433
Screening Study Complete44908
Fis Approved45909
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.