Substation Scout

Leon BESS

ERCOT queue ID 25INR0693

Leon BESS (25INR0693) is listed in the ERCOT interconnection queue as a 153.7 MW battery project in Leon County, TX. The filing names Tab Grapeland_Magnolia - Pleasant_Springs. as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of February 16, 2028. It records the screening study as complete on February 18, 2025.

Queue ID25INR0693
Project nameLeon BESS
Status (as published)SS Completed, FIS Started, No IA
SubstationTab Grapeland_Magnolia - Pleasant_Springs.
Point of interconnectionTab 138kv 3355 Grapeland_Magnolia - 3357 Pleasant_Springs.
CountyLeon
StateTX
Voltage138 kV
Capacity153.7 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-02-16
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Leon, TX: 14 requests in the ERCOT queue, 13 active totaling 6,147.5 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityLeon BESS
CDR reporting zoneNORTH
Fuel codeOTH
Technology codeBA
Screening study complete2025-02-18

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first